Our data center provider 1-Net Singapore is scheduling a network maintenance as follows:


FROM: 19th March 2016 (Saturday) at 00:00hrs (Singapore time, GMT +0800)
TO: 19th March 2016 (Saturday) at 04:00hrs (Singapore time, GMT +0800)
MAINTENANCE DURATION: 4 hours
SERVICE IMPACT DURATION: 15 minutes


Click here to convert the above time to your time zone:


http://www.timeanddate.com/worldclock/converter.html


Impact: Intermittent Internet connectivity disruption up to 15 minutes.


Activities to be performed: Hardware upgrade on 1-Net Network Infrastructure


Affected links: One of the links to 1-Net transit. Traffic will automatically be re-routed to the other available link. Local connectivity to Singapore Internet Exchange (SGIX) is not affected.


Please feel free to open up a support ticket with us if you have further enquiries.